3 day tile project photo log.
Day 1: demo, new plywood sub-floor, thin-set & cement board install.
Day 2: Tile layout and mock-up, thin-set, install tile.
Day 3: Grout tile joints, install base-board, door transition, paint touch-ups, install toilet.
in-process photos. tile is 6"x36" plank installed in a 1/3 running bond pattern.
No comments: